Rewa Bypass

Name of Project

:

Rewa Bypass (NH-7)

Type of Project

:

Toll

Project Description

:

New 2-Lane Bypass for Rewa City

Concessioning Authority

:

Ministry of Road Transport & Highways (MoRTH)

Concessionaire

:

Path Oriental Highways Limited

Project Length

:

19.80 Km

Concession Period

:

14.66 Years (5351 Days)

Construction Period

:

24 months

Total Project Cost

:

INR 50.08 Crores

Debt

:

INR 36.00 Crores

Equity

:

INR 12.00 Crores

Oriental's Stake in the Project SPV

:

50%

JV Partners (if any)

:

Prakash Asphalting & Toll Highways Limited (PATH)

Appointed Date

:

23rd July 2005

Commercial Operations Date (COD)

:

27th April 2007

Project Lenders

: